Brief Description of Project

Heath Engineering Company provided HVAC system design, plumbing and fire protection design for the new underground library facility. The overall construction cost was $31 million. The mechanical construction cost was approximately $5 million. The mechanical systems included a 1,200 ton central chilled water plant, and connection into the central campus high temperature water system.
The high temperature water is used to produce building heating water with a capacity of 12,000,000 Btuh.
To conserve energy the lowest kw/ton chiller was used.
Minimum outside air fans were used to control ventilation while keeping the outside air volume as low as possible

 

Project Team
Jeffrey S. Anderson, P.E.
Project Engineer
Executive Vice President
801.322.0487

Larry D. Veigel, P.E.
President
Mechanical Engineer

Randall T. Veigel, P.E.
Administrative Vice President
Mechanical Engineer

Robert J. Kesler
Plumbing Designer


Reference

Robert L. Davis, Jr. AIA
BSHA

Architecture
Planning
Interior Design
Engineering
919 Fourth Avenue, Suite 200
San Diego, California 92101

Burtch W. Beall, Jr.
2188 Highland Dr. Suite 208
Holladay, Utah 84106



Name of Project
Marriott Library Addition
University of Utah
Salt Lake City, Utah

Owner/Agency
University of Utah

Design Start/End Dates
April 1992/January 1998

Services Provided
Mechanical Engineering
Plumbing Engineering
Fire Protection

Construction Delivery Type
Design – Bid – Build

Building Project Cost
$31,000,000

Total Square Footage
200,000 Square Feet

 

 

 

 